📊 Earned Value Management Calculator
احسب جميع مؤشرات أداء المشروع تلقائياً
املأ المدخلات لتفوز بالنتائج والـ Dashboard الاحترافي
🔢 Inputs
Value of work planned to be completed by today
Value of work actually completed
Actual cost of work completed
Total project budget
📈 Results
Enter values in the input fields and click "Calculate Metrics"
📈 Executive Dashboard
💰 BAC
-
Budget at Completion
📋 PV
-
Planned Value
✅ EV
-
Earned Value
💵 AC
-
Actual Cost
📊 CV
-
Cost Variance
⏱️ SV
-
Schedule Variance
🎯 EAC
-
Estimate at Completion
📉 VAC
-
Variance at Completion
CPI - Cost Performance Index
-
SPI - Schedule Performance Index
-
📊 Charts
📉 S-Curve
📚 Quick Reference Guide
Calculated Metrics:
- CV (Cost Variance): Cost deviation = EV - AC
- SV (Schedule Variance): Schedule deviation = EV - PV
- CPI (Cost Performance Index): Cost efficiency = EV / AC
- SPI (Schedule Performance Index): Schedule efficiency = EV / PV
- EAC (Estimate at Completion): Forecasted total cost = BAC / CPI
- ETC (Estimate to Complete): Cost to finish = EAC - AC
- VAC (Variance at Completion): Budget deviation = BAC - EAC
- TCPI (To-Complete Performance Index): Required efficiency = (BAC - EV) / (BAC - AC)
Reading Results:
- ✅ Good: CPI > 1.0 or SPI > 1.0 (Good performance)
- ⚠️ Warning: 0.9 < CPI/SPI < 1.0 (Acceptable)
- ❌ Critical: CPI < 0.9 or SPI < 0.9 (Poor performance)