Before any column or wall is built, there's a simple yet essential concrete layer placed at the bottom of the excavation. This layer is called "Blinding Concrete" or Plain Concrete (P.C) - and it's the first element cast in any building. In this article, we'll cover everything you need to know to execute it correctly.

What is Blinding Concrete?

Blinding concrete is a layer of unreinforced plain concrete cast directly on the soil at the bottom of excavation, beneath reinforced foundations (footings or raft). It's also known as:

💡 Important Note

Some confuse "Blinding Concrete" (plain concrete under foundations) with "Batter Board (Khanzira)" (wooden frame for setting out axes). This article covers blinding concrete only. To learn more about batter boards, click here.

Why Do We Need Blinding Concrete?

Some might ask: Why not cast reinforced foundations directly on soil? The answer is that blinding concrete serves several vital functions:

1. Providing a Level Working Surface

Natural soil is never perfectly level even after grading. Blinding concrete provides a perfectly horizontal surface that makes working easier and allows precise reinforcement placement.

2. Protecting Reinforcement Steel

Without blinding concrete, the bottom reinforcement of footings would contact the soil directly, exposing it to moisture and corrosion. Blinding concrete ensures adequate concrete cover.

3. Preventing Cement Paste Loss

When casting reinforced foundations, blinding concrete prevents the cement paste (water and cement) from seeping into the soil, maintaining concrete quality.

4. Facilitating Formwork and Reinforcement Work

The hard and level surface makes installing formwork and placing reinforcement chairs at the correct height much easier.

5. Verifying Excavation Levels

Blinding concrete helps confirm correct excavation levels, as measurements are taken immediately after casting.

Technical Specifications

Item Specification Notes
Thickness 10 - 15 cm 10 cm most common for normal buildings
Concrete Grade C15 (15 MPa) Sometimes C10 for small projects
Mix Ratio 1 : 3 : 6 Cement : Sand : Gravel
Aggregate Size Up to 40 mm Can use relatively large aggregate
Extension Beyond Footing 10 - 15 cm each side To facilitate formwork installation

✅ Site Tip

For large projects, ready-mix concrete is preferred to ensure consistent quality. For small projects, site mixing is acceptable if proper mix ratios are maintained.

Execution Steps

1

Verify Excavation Level

Before anything else, confirm the excavation bottom is at the correct level using a dumpy level or total station. Record readings in a report.

2

Clean Excavation Bottom

Remove any loose materials, wet mud, or large stones. The bottom should be clean and compact.

3

Compact if Necessary

If the soil is loose or has been backfilled, compact it well with a compactor before casting.

4

Water Spraying

Spray the soil with water just before casting to prevent it from absorbing concrete water. Don't flood it, just moisten it.

5

Place Side Forms

Wooden boards can be used on the sides to define casting boundaries and ensure the required thickness.

6

Pour Concrete

Pour and spread concrete with trowels and wooden screed. Ensure the entire area is covered with uniform thickness.

7

Leveling

Level the surface using a screed board. No smooth finish is required, but it must be level.

8

Curing

Cover the concrete with wet burlap or plastic, and spray with water for at least 3 days.

Common Mistakes and How to Avoid Them

⚠️ Mistake #1: Casting on Uncompacted Soil

Result: Uneven settlement and foundation cracks.
Solution: Ensure proper soil compaction before casting, especially in backfill areas.

⚠️ Mistake #2: Thickness Less Than Required

Result: Inadequate protection for footing reinforcement.
Solution: Use side forms and carefully control levels.

⚠️ Mistake #3: Not Extending Beyond Footing Boundaries

Result: Difficulty installing formwork.
Solution: Cast blinding concrete 10-15 cm beyond footing dimensions on all sides.

⚠️ Mistake #4: Leaving Blinding Concrete Without Curing

Result: Surface cracking and weak concrete.
Solution: Water curing for 3-7 days.

Inspections and Handover

Before starting reinforced footing work on the blinding concrete, verify:

  1. Level: Confirm the blinding surface level matches the design.
  2. Flatness: Use a level to check surface evenness.
  3. Thickness: Take measurements at multiple points to confirm required thickness.
  4. Dimensions: Ensure blinding extends sufficiently beyond footing boundaries.
  5. Setting: Wait until concrete has set adequately (24-48 hours) before working on it.

✅ Handover Documentation

Ensure blinding concrete acceptance is documented in an official report signed by the supervising engineer, including: date, levels, thickness, and inspection notes.

Next Element in the Series

🔜 Coming Up: Reinforced Footings

After blinding concrete has set, we move to the next phase: reinforced footings (isolated or combined). We'll cover: footing types, reinforcement detailing, casting, and common mistakes.

Quick Summary

🧪 Test Your Knowledge

1. What is the common thickness for blinding concrete in normal buildings?

2. Why should blinding concrete extend beyond footing boundaries?

3. What is the common concrete grade for blinding concrete?